There are 2 main approaches to solve this problem:
Let's start by understanding the problem: we need to find the maximum capital we can accumulate by completing at most k projects, where each project requires a minimum capital to start and yields a profit upon completion.
Thinking Process: The most straightforward approach would be to try all possible combinations of at most k projects and find the one that maximizes the final capital. However, this would be extremely inefficient as there are potentially exponentially many combinations.
A slightly better brute force approach would be to simulate the process: at each step, we consider all available projects (those with required capital less than or equal to our current capital), choose the one with the highest profit, complete it, update our capital, and repeat until we've completed k projects or there are no more available projects.
Intuition: This approach directly follows the problem statement. We greedily choose the project with the highest profit among all available projects at each step. However, the inefficiency comes from having to scan all projects at each step to find the available ones and the one with the highest profit.
Where k is the maximum number of projects and n is the total number of projects. In the worst case, we need to scan all n projects k times to find the one with the highest profit.
We need O(n) space to keep track of which projects have been completed.
We can optimize the brute force approach by using two priority queues (heaps) to efficiently track available projects and find the one with the highest profit.
Thinking Process: The key insight is that we need to efficiently track two things:
We can use a min heap to sort projects by their required capital and a max heap to sort available projects by their profit. At each step, we move all newly available projects from the min heap to the max heap, then choose the project with the highest profit from the max heap.
Intuition: By using two heaps, we avoid scanning all projects at each step. The min heap allows us to efficiently find projects that become available as our capital increases, and the max heap allows us to efficiently find the project with the highest profit among all available projects.
Where n is the total number of projects. Adding all projects to the capitalHeap takes O(n log n) time. In the worst case, we might move each project from the capitalHeap to the profitHeap once, which takes O(n log n) time. Removing at most k projects from the profitHeap takes O(k log n) time. Since k ≤ n, the overall time complexity is O(n log n).
We need O(n) space to store all projects in the heaps.
1234567891011121314151617181920function findMaximizedCapital(k, w, profits, capital): currentCapital = w completed = new Set() for i from 1 to k: maxProfit = 0 maxProfitIndex = -1 for j from 0 to profits.length - 1: if j not in completed and capital[j] <= currentCapital and profits[j] > maxProfit: maxProfit = profits[j] maxProfitIndex = j if maxProfitIndex == -1: break currentCapital += maxProfit completed.add(maxProfitIndex) return currentCapital
Understand different approaches to solve the capital investment optimizer problem and analyze their efficiency.
Let's start by understanding the problem: we need to find the maximum capital we can accumulate by completing at most k projects, where each project requires a minimum capital to start and yields a profit upon completion.
Thinking Process: The most straightforward approach would be to try all possible combinations of at most k projects and find the one that maximizes the final capital. However, this would be extremely inefficient as there are potentially exponentially many combinations.
A slightly better brute force approach would be to simulate the process: at each step, we consider all available projects (those with required capital less than or equal to our current capital), choose the one with the highest profit, complete it, update our capital, and repeat until we've completed k projects or there are no more available projects.
Intuition: This approach directly follows the problem statement. We greedily choose the project with the highest profit among all available projects at each step. However, the inefficiency comes from having to scan all projects at each step to find the available ones and the one with the highest profit.
We can optimize the brute force approach by using two priority queues (heaps) to efficiently track available projects and find the one with the highest profit.
Thinking Process: The key insight is that we need to efficiently track two things:
We can use a min heap to sort projects by their required capital and a max heap to sort available projects by their profit. At each step, we move all newly available projects from the min heap to the max heap, then choose the project with the highest profit from the max heap.
Intuition: By using two heaps, we avoid scanning all projects at each step. The min heap allows us to efficiently find projects that become available as our capital increases, and the max heap allows us to efficiently find the project with the highest profit among all available projects.
Where k is the maximum number of projects and n is the total number of projects. In the worst case, we need to scan all n projects k times to find the one with the highest profit.
We need O(n) space to keep track of which projects have been completed.
Where n is the total number of projects. Adding all projects to the capitalHeap takes O(n log n) time. In the worst case, we might move each project from the capitalHeap to the profitHeap once, which takes O(n log n) time. Removing at most k projects from the profitHeap takes O(k log n) time. Since k ≤ n, the overall time complexity is O(n log n).
We need O(n) space to store all projects in the heaps.
1234567891011121314151617181920function findMaximizedCapital(k, w, profits, capital): currentCapital = w completed = new Set() for i from 1 to k: maxProfit = 0 maxProfitIndex = -1 for j from 0 to profits.length - 1: if j not in completed and capital[j] <= currentCapital and profits[j] > maxProfit: maxProfit = profits[j] maxProfitIndex = j if maxProfitIndex == -1: break currentCapital += maxProfit completed.add(maxProfitIndex) return currentCapital
12345678910111213141516171819202122232425function findMaximizedCapital(k, w, profits, capital): currentCapital = w // Create a min heap of projects sorted by required capital capitalHeap = new MinHeap() for i from 0 to profits.length - 1: capitalHeap.add([capital[i], profits[i]]) // Create a max heap of available projects sorted by profit profitHeap = new MaxHeap() for i from 1 to k: // Move all available projects from capitalHeap to profitHeap while capitalHeap is not empty and capitalHeap.peek()[0] <= currentCapital: [cap, profit] = capitalHeap.poll() profitHeap.add(profit) // If no projects are available, break if profitHeap is empty: break // Complete the project with the highest profit currentCapital += profitHeap.poll() return currentCapital
There are 2 main approaches to solve this problem:
Let's start by understanding the problem: we need to find the maximum capital we can accumulate by completing at most k projects, where each project requires a minimum capital to start and yields a profit upon completion.
Thinking Process: The most straightforward approach would be to try all possible combinations of at most k projects and find the one that maximizes the final capital. However, this would be extremely inefficient as there are potentially exponentially many combinations.
A slightly better brute force approach would be to simulate the process: at each step, we consider all available projects (those with required capital less than or equal to our current capital), choose the one with the highest profit, complete it, update our capital, and repeat until we've completed k projects or there are no more available projects.
Intuition: This approach directly follows the problem statement. We greedily choose the project with the highest profit among all available projects at each step. However, the inefficiency comes from having to scan all projects at each step to find the available ones and the one with the highest profit.
Where k is the maximum number of projects and n is the total number of projects. In the worst case, we need to scan all n projects k times to find the one with the highest profit.
We need O(n) space to keep track of which projects have been completed.
We can optimize the brute force approach by using two priority queues (heaps) to efficiently track available projects and find the one with the highest profit.
Thinking Process: The key insight is that we need to efficiently track two things:
We can use a min heap to sort projects by their required capital and a max heap to sort available projects by their profit. At each step, we move all newly available projects from the min heap to the max heap, then choose the project with the highest profit from the max heap.
Intuition: By using two heaps, we avoid scanning all projects at each step. The min heap allows us to efficiently find projects that become available as our capital increases, and the max heap allows us to efficiently find the project with the highest profit among all available projects.
Where n is the total number of projects. Adding all projects to the capitalHeap takes O(n log n) time. In the worst case, we might move each project from the capitalHeap to the profitHeap once, which takes O(n log n) time. Removing at most k projects from the profitHeap takes O(k log n) time. Since k ≤ n, the overall time complexity is O(n log n).
We need O(n) space to store all projects in the heaps.
1234567891011121314151617181920function findMaximizedCapital(k, w, profits, capital): currentCapital = w completed = new Set() for i from 1 to k: maxProfit = 0 maxProfitIndex = -1 for j from 0 to profits.length - 1: if j not in completed and capital[j] <= currentCapital and profits[j] > maxProfit: maxProfit = profits[j] maxProfitIndex = j if maxProfitIndex == -1: break currentCapital += maxProfit completed.add(maxProfitIndex) return currentCapital
Understand different approaches to solve the capital investment optimizer problem and analyze their efficiency.
Let's start by understanding the problem: we need to find the maximum capital we can accumulate by completing at most k projects, where each project requires a minimum capital to start and yields a profit upon completion.
Thinking Process: The most straightforward approach would be to try all possible combinations of at most k projects and find the one that maximizes the final capital. However, this would be extremely inefficient as there are potentially exponentially many combinations.
A slightly better brute force approach would be to simulate the process: at each step, we consider all available projects (those with required capital less than or equal to our current capital), choose the one with the highest profit, complete it, update our capital, and repeat until we've completed k projects or there are no more available projects.
Intuition: This approach directly follows the problem statement. We greedily choose the project with the highest profit among all available projects at each step. However, the inefficiency comes from having to scan all projects at each step to find the available ones and the one with the highest profit.
We can optimize the brute force approach by using two priority queues (heaps) to efficiently track available projects and find the one with the highest profit.
Thinking Process: The key insight is that we need to efficiently track two things:
We can use a min heap to sort projects by their required capital and a max heap to sort available projects by their profit. At each step, we move all newly available projects from the min heap to the max heap, then choose the project with the highest profit from the max heap.
Intuition: By using two heaps, we avoid scanning all projects at each step. The min heap allows us to efficiently find projects that become available as our capital increases, and the max heap allows us to efficiently find the project with the highest profit among all available projects.
Where k is the maximum number of projects and n is the total number of projects. In the worst case, we need to scan all n projects k times to find the one with the highest profit.
We need O(n) space to keep track of which projects have been completed.
Where n is the total number of projects. Adding all projects to the capitalHeap takes O(n log n) time. In the worst case, we might move each project from the capitalHeap to the profitHeap once, which takes O(n log n) time. Removing at most k projects from the profitHeap takes O(k log n) time. Since k ≤ n, the overall time complexity is O(n log n).
We need O(n) space to store all projects in the heaps.
1234567891011121314151617181920function findMaximizedCapital(k, w, profits, capital): currentCapital = w completed = new Set() for i from 1 to k: maxProfit = 0 maxProfitIndex = -1 for j from 0 to profits.length - 1: if j not in completed and capital[j] <= currentCapital and profits[j] > maxProfit: maxProfit = profits[j] maxProfitIndex = j if maxProfitIndex == -1: break currentCapital += maxProfit completed.add(maxProfitIndex) return currentCapital
12345678910111213141516171819202122232425function findMaximizedCapital(k, w, profits, capital): currentCapital = w // Create a min heap of projects sorted by required capital capitalHeap = new MinHeap() for i from 0 to profits.length - 1: capitalHeap.add([capital[i], profits[i]]) // Create a max heap of available projects sorted by profit profitHeap = new MaxHeap() for i from 1 to k: // Move all available projects from capitalHeap to profitHeap while capitalHeap is not empty and capitalHeap.peek()[0] <= currentCapital: [cap, profit] = capitalHeap.poll() profitHeap.add(profit) // If no projects are available, break if profitHeap is empty: break // Complete the project with the highest profit currentCapital += profitHeap.poll() return currentCapital